CriticalDevelopment

Data center regulations in the Unified Development Code

Residents pressed for a town hall and a count of how much of Cheyenne will be data centers; staff agreed to calculate the percentage before the next committee meeting.

9 mentions (1 this month)Last discussed Oct 12, 2026
CriticalTaxes Budget

Fiscal Year 2026-2027 City Budget and Tax Appropriation

The council adopted its project list for the optional 1% sales tax on the November ballot for 2027-2030. Roughly 80% goes to roads and 9% to police and fire — voters decide in November.

2 mentionsLast discussed Sep 28, 2026
CriticalDevelopment

Cox Ranch annexation and Skybox data center

A 1,200-acre owner-initiated annexation west of Roundtop Road tied to a possible Via West/Skybox data center drew hours of opposition from Rolling Hills and west-side residents over water, traffic, noise, wildlife and trust in the process. Council postponed it and its two zoning companions to September 14, 2026.

34 mentionsLast discussed Sep 28, 2026
CriticalZoning

Orchard Hills annexation (162 acres)

Yet another data center annexation — 162 acres near Orchard Valley — advanced on second reading, with Trammell Crow promising a 500-foot buffer, greenway extension and road improvements. Neighbors remain split between fearing housing traffic and fearing more Meta-style light pollution.

9 mentions (1 this month)Last discussed Sep 28, 2026
CriticalEnvironment

Meta wastewater contamination disclosure

A February contamination of the reclaimed water system by a data center contractor — involving antibiotic-resistant bacteria — was not publicly disclosed until July 9. Speakers demanded answers on timing and accountability; a BOPU engineer said drinking water was never at risk and a full timeline is coming.

5 mentionsLast discussed Jul 13, 2026
CriticalDevelopment

Microsoft Highlands Data Center Annexation

The council approved the largest annexation in Cheyenne's history — 3,459.99 acres — plus Business Park zoning, opening the door to a massive Microsoft data center campus near Sweetgrass. Most public speakers opposed it, citing water, noise, and lost negotiating leverage; supporters cited jobs and tax revenue.

14 mentionsLast discussed Jul 13, 2026
CriticalGovernance

Twelve-Month Data Center Moratorium

The city is weighing a one-year pause on new data centers after explosive growth since 2021 — ten operating, five under construction, nine announced. Residents cited water, power-grid strain, noise, health and transparency concerns; unions, businesses and utilities argued jobs and investment are at stake. The moratorium failed 1-8 but the debate will clearly continue.

13 mentionsLast discussed May 26, 2026