Microsoft Highlands Data Center Annexation
Summary
The council approved the largest annexation in Cheyenne's history — 3,459.99 acres — plus Business Park zoning, opening the door to a massive Microsoft data center campus near Sweetgrass. Most public speakers opposed it, citing water, noise, and lost negotiating leverage; supporters cited jobs and tax revenue.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Jul 13, 2026.
Impact analysis
Microsoft is already the city's top taxpayer at roughly $11 million a year in property tax, and the annexation brings more tax base but also infrastructure obligations.
Landowners selling the property, Microsoft, construction and tech workers, and the city's tax base.
Nearby Sweetgrass and county residents fear noise, water strain, and property value losses; the city loses negotiating leverage once land is zoned.
Mentions & discussions (6)
Petition organizers criticize Cheyenne council’s move to challenge Microsoft annexation referendum
Petition organizers criticize Cheyenne council’s move to challenge Microsoft annexation referendum WyomingNews.com
Cheyenne City Council approves Microsoft's 3,460-acre annexation after hours of public debate
Cheyenne City Council approves Microsoft's 3,460-acre annexation after hours of public debate WyomingNews.com
City Council Meeting - Jul 13, 2026
The council approved the largest annexation in Cheyenne's history — 3,459.99 acres — plus Business Park zoning, opening the door to a massive Microsoft data center campus near Sweetgrass. Most public speakers opposed it, citing water, noise, and lost negotiating leverage; supporters cited jobs and tax revenue.
City Council Meeting - Jun 23, 2026
The council advanced the largest annexation in city history — about 3,460 acres for a possible Microsoft data center campus. Residents packed the room with concerns about water, noise, lights, and whether the city should demand a community benefits agreement before annexing. A four-month delay to negotiate a deal failed 3-6.
City Council Meeting - Jun 8, 2026
The city is being asked to annex nearly 3,500 acres east of South Greeley Highway for what residents widely understand will be a Microsoft data center campus. Residents raised water supply, quality-of-life, and process concerns; Wolfe pushed for community-benefit conditions while the mayor argued annexation only changes the map. No vote yet — it heads to committee.
Microsoft plans massive 3,200-acre expansion of Cheyenne data centers
Microsoft plans massive 3,200-acre expansion of Cheyenne data centers Oil City News
Related development
Highlands annexation (3,459.99 acres)
Could be the largest annexation in city history and shape the city's south side for decades; opponents cite water and quality-of-life risks.
South Greeley Highway / Sweetgrass Area Annexation and Rezone
A massive annexation that would open thousands of acres southeast of town for business park development.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.