5th and Main Curb Reconstruction

Summary

The tight curb radius at 5th and Main has trucks bumping or even jumping the curb and driving over the ADA ramp. A $73,637.50 contract with SSR Construction will widen the radius to 44 feet this fall, funded by the extra penny sales tax.

At a glance

Total mentions
2
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Oct 5, 2026.