Project Tembo HUB-1 Office Support Facility
Description
Google's data center project got a Class B conditional use permit to build an employee office, dining, and parking facility on 32.83 acres not covered by its original PUD zoning.
Impact summary
Nothing changes yet — the project will come back to the commission at a later meeting.
Applicant
- Name
- Project Tembo (Jupiter Star Holdings LLC; agent HDR Engineering Inc.)
- Address
- Tracts 1 & 2, Cold Creek Buffalo Company Subdivision, Laramie County, WY
At a glance
- Hearings
- 2
- Public comments
- 0
- Total mentions
- 2
Last vote · Planning Commission
Discussed at 1 meeting in the last 60 days; most recently Sep 10, 2026.
Meeting timeline (2)
Planning Commission — September 10, 2026
Google's data center project got a Class B conditional use permit to build an employee office, dining, and parking facility on 32.83 acres not covered by its original PUD zoning.
Planning Commission — August 13, 2026
The applicant asked to postpone the hearing while a site plan amendment is underway, so no action was taken beyond the delay.
Related issues (1)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Laramie County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.